| Project Name | Construction of 4 lane Access Controlled New Greenfield Highway Section of NH-365BG (Khammam-Devarapalle) of length 33.604 km from Thallampadu village to Somavaram village (Design Chainage 0+000 to 33+604) under Inter Corridor Route under Bharatmala Pariyojana, on Hybrid Annuity mode in the state of Telangana (Package-I) |
| Total Bid Project Cost: | 772.11 Cr. (Incl GST) |
| Project Total Length: | 33.604 Kms |
| Pavement Type: | Flexible |
| No of Lanes: | 4 |
| Right of Way: | 60 Meter |
| Date of LOA: | 15th September 2021 |
| Date of Agreement: | 28th August 2022 |
| Date of Appointment: | 31st October 2022 |
| Date of Completion: | 29th October 2024 |
| Completion Period: | 24 months from date of Appointment |
| Client: | National Highways Authority of India (NHAI) |
| Concessionaire: | H.G. Khammam Devarapalle Pkg-1 Private Limited |
| EPC Contractor: | H.G.INFRA ENGINEERING LTD. |
| Independent Engineer: | LEA Associates South Asia Pvt. Ltd |
| Project Model Type: | Hybrid Annuity Mode (HAM) |
| Maintenance Period: | 15 Years |
| Project Name | Construction of 4 lane Access Controlled New Greenfield Highway Section of NH-365BG (Khammam-Devarapalle) of length 33.604 km from Thallampadu village to Somavaram village (Design Chainage 0+000 to 33+604) under Inter Corridor Route under Bharatmala Pariyojana, on Hybrid Annuity mode in the state of Telangana (Package-I) |
| Total Bid Project Cost: | 772.11 Cr. (Incl GST) |
| Project Total Length: | 33.604 Kms |
| Pavement Type: | Flexible |
| No of Lanes: | 4 |
| Right of Way: | 60 Meter |
| Date of LOA: | 15th September 2021 |
| Date of Agreement: | 28th August 2022 |
| Date of Appointment: | 31st October 2022 |
| Date of Completion: | 29th October 2024 |
| Completion Period: | 24 months from date of Appointment |
| Client: | National Highways Authority of India (NHAI) |
| Concessionaire: | H.G. Khammam Devarapalle Pkg-1 Private Limited |
| EPC Contractor: | H.G.INFRA ENGINEERING LTD. |
| Independent Engineer: | LEA Associates South Asia Pvt. Ltd |
| Project Model Type: | Hybrid Annuity Mode (HAM) |
| Maintenance Period: | 15 Years |